Home | Contact Us | Low Graphic Version
About UsLanguageEducationcultureAwarenessAbout WorselsleidFowkgatesLearAwaur

Overview


Corporate Plan 2005-2007


Corporate Plan 2000/1 - 2003/4

Mission Statement/Background
Organisation
The Board
Policy Context
Opportunities & Challenges
Vision, Objectives & Targets
Operating Principles
Resources

Board Members


Chief Executive


Staff


Annual Report 2000


Grants


Complaints


Press Releases


Freedom of Information Act


European Charter


Latest Vacancies


2006 Business Plan


Board Meeting Minutes


 


Background

The Ulster-Scots Agency currently employs four members of staff - reflecting the fact that the Agency is in a start-up phase. In order to be in a position to deliver the programme of work contained in this Corporate Plan, the Agency will need to recruit new members of staff. An Organisation Chart setting out the revised staffing structure of the Ulster-Scots Agency is shown at Annex 1.

The Ulster-Scots Agency is funded by grants from the Department of Culture, Arts and Leisure in Northern Ireland and the Department of Arts, Heritage, Gaeltacht and the Islands in the Republic of Ireland.

In the calendar year 2000, this funding amounts to £0.67 million to cover programme costs, staff salaries and running costs. For the period 2001/02 to 2003/04, the Ulster-Scots Agency has calculated the costs of the programme at £4.20 million. The figure for the start-up year, 2001/02 is estimated at £1.3 million.

Staff Salaries and Running Costs.

Of the total funding requirement of £1.45 million, £0.555 million is to cover staff salaries and running costs. A breakdown of salary and running costs is shown in Table 1 below:

Table 1:
Staff Salaries and Running Costs - 2001/02
Area of Expenditure
£K
Staff Salaries
317
Board Members' Remuneration
50
General Administration Expenses
70
Accommodation
40
Travel and Subsistence
30
IT Equipment and Support
20
Other Costs (eg consultancy support)
28s
Total:
555



Programme Expenditure

The remaining £0.895 million is for programme expenditure. A breakdown of programme expenditure across the four main areas of operation (strategic objectives) of the Agency is shown in Table 2 below:

Table 2:
Programme Expenditure - 2001/02
No. Theme Programme
£K
1. Linguistic Dictionary and Development Surveys
475
2. Culture Cultural Support Grants
125
3. Education School of Ulster-Scots Studies
100
4. Educational programmes and materials etc.
100
5.Promoting Acceptance Marketing and Promotional Programm
95
Total Programme Expenditure
895



Funding by Theme/Objective

After the allocation of all direct costs and apportionment of central support costs, the Agency's total funding requirement of £1.45 million is broken down as follows across its four main areas of operation:

Table 3:
Expenditure by Objective - 2001/02
No. Objective
£K
1. Linguistic Development
567.5
2. Culture
262.5
3. Education
432.5
4. Promoting Acceptance
187.5
Total
1,450